Upgrading Of Hydro Turbine Governor Control System (Unit 1, 2, 3) At Tenom Power Plant, Sabah

The first Power Generation project won by PESTECH.

Upgrading of Hydro Turbine Governor Control System at Tenom Pangi Hydro Electric Power Plant owned by Sabah Electricity Sdn. Bhd. We successfully replaced existing Hydraulic Control System and Turbine Governor Control System with Valmet DNA Distributed Control System (DCS) for Unit 1, 2, 3 within 15 months. The first unit, Unit 1 system been delivered within 4 months from date of award. For Unit 1, project started commencement in January 2015 and completed in April 2015, with a superfast track progress. While for Unit 2 and Unit 3 commencement started in July 2015, followed by Unit 2 in April 2016.